Using our Ditch Witch JT60 Drilling Machine we successfully installed 4 x 225mm Electric ducts to a depth below 3 meters under the A52 Nottingham . GMAC Utilities Ltd were responsible for organising the excavation , pipe welding and drilling teams. We also liaised with Highways England to ensure a safe Traffic Management System was in place for the works. All works were carried out day and night due to the traffic loads on the A52 during the day. Our team butt welded and internally debeaded the ducts before installation. Our team located all known utilities and services along the drill path before drilling. It took the team four days and three nights  to install 4 x  225mm SDR11 Ducts under the A52 Clifton Boulevard. The works were carried out on behalf of the contractor Green Frog Connect for the client Western Power Distribution.

 

 

 